SAP PS Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP PS. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - Arrange the below steps in correct order in Project implementation?

1. Create Project

2. Project Planning

3. Project Completion

4. Budgeting and Release

5. Project Implementation

6. Create Templates/WBS

A - 1,2,3,4,5,6

B - 6,1,2,4,5,3

C - 6,1,2,5,4,3

D - 6,1,4,2,5,3

Answer : B

Explanation

Below are the key steps involved in Project process flow:

  • Create Templates/WBS
  • Create Project
  • Project Planning
  • Budgeting and Release
  • Project Implementation
  • Project Completion

Q 2 - In Project system, it is also possible to assign any object currency to which of the following objects in the system?

A - WBS element

B - Project definition

C - Network header

D - Network activity

E - All of the above

Answer : E

Explanation

Object currency:

In Project system, it is also possible to assign any object currency to different objects in the system.

  • WBS element
  • Project definition
  • Network header
  • Network activity

Q 3 - Which of the following Transaction Code is used to define PS text types in SAP system?

A - OPSK

B - OPS3

C - OK02

D - OK03

Answer : B

Q 4 - In a project, you collect cost and revenues temporarily and they have to settle as part of period end processing. You need a profile type?

A - Default Profile

B - Project Profile

C - Settlement Profile

D - Selection Profile

Answer : C

Answer : B

Q 6 - The information entered in project profile is copied to project in project definition or also in the project elements and can be changed at later stage?

A - True

B - False

Answer : A

Q 7 - In PS system, you can use the settlement profile to define the following for actual costs?

A - Full Settlement

B - Can be settled

C - Not to be settled

D - All of the above

Answer : D

Explanation

You use the settlement profile to define the following for actual costs:

  • Full Settlement
  • Can be settled
  • Not to be settled

Q 8 - Using Control key in SAP PS system, you can determine the business transactions to be performed when you perform an activity?

A - True

B - False

Answer : A

Q 9 - Consider a user A is assigned to user group 1 that has read authorization for a PS object and user has change authorization for PS object. The user gets?

A - Read Authorization

B - Change Authorization

C - Both of the above

Answer : B

Explanation

Consider a user A is assigned to user group 1 that has read authorization for a PS object and user has change authorization for PS object. The user gets change authorization in this scenario.

Q 10 - In SAP PS, which of the following project version is used to store different cost plans for a project?

A - Project Versions

B - Plan Versions

C - Selection Versions

D - Simulation Versions

Answer : B

Explanation

There are different project versions types available in Project System:

Project Versions:

To compare project status at specific time period.

Plan Versions:

This is sued to store different cost plans for a project.

Selection Versions:

This is used to perform background processing and to save the project data matching certain selection criteria.

Simulation Versions

In below table, you can see the different features in a project that above versions supports in SAP system.

sap_ps_questions_answers.htm