Following quiz provides Multiple Choice Questions (MCQs) related to SAP CCA. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Answer : D

Explanation

Controlling can be implemented independently of FI, there is some basic configuration that needs to be done in FI.

Q 2 - Which of the following resource type can be used for Overhead Cost Controlling?

A - Type R

B - Type M

C - Type B

D - Type D

Answer : A

Q 3 - Which of the following can be used to copy actuals to a target planning version?

A - Cost Center

B - Cost Element

C - Actual Version

D - All of the above

Answer : A

Q 4 - If you are able to create a primary cost element in SAP CO system. What would you check first?

A - A Valid Cost Element Category exists

B - P/L account exists

C - G/L has the same currency as Controlling Area.

D - All of the above

Answer : B

Q 6 - To create a Profit Center, Use T-code: KE51 or go to Accounting → Controlling → Profit Center Accounting → Master Data → Profit Center → Individual Processing → Create?

A - True

B - False

Answer : A

Q 7 - In which of the following process, you need to transfer the data from other SAP components and post in Finance Accounting?

A - Cost Center Planning

B - Period End closing

C - Actual Cost Accounting

D - Cost Center Groups

Answer : B

Explanation

Period end closing is work carried out at period end as part of cost controlling. To perform period end closing, it is required to transfer the data from other SAP components. You should perform all the posting in Finance Accounting.

Q 8 - Which of the following transaction code is used for Product Costing?

A - KAH1

B - KP01

C - KP11

D - KH1

Answer : B

Q 9 - To execute the reports you have to navigate to Information Systems → Accounting → Controlling → Reports for Cost Center Accounting?

A - True

B - False

Answer : A

Q 10 - When you create the activity types, prices of these can be entered?

A - Manually

B - Calculated in system as per the cost allocated

C - Both of these

Answer : C